|
Capital
Improvement Projects
UPDATE: Calder
Street Project
Update for the week of
November 2, 2009
The Calder Street Project Phase I
began construction on July 7, 2008. The project limits
of this phase of the project are from the Neches River
to just west of ML King Parkway. The Box Installation
has been completed for the South and North runs from the
Neches River to the end of the project. Reytec plans on
having the M.L. King / Calder intersection open with the
traffic signals in operation this week.
The concrete pavement has been
installed on Calder to the radii of return on M.L. King.
Reytec plans on installing brick pavers, decorative
lighting, traffic signals, landscaping and bicycle lanes
on Calder Avenue as part of the project. Reytec
continues to install signage from Main St. to M.L. King
on Calder Avenue this week. Reytec continues to work on
the section of pavement from Magnolia Avenue to M.L.
King on Calder.
Calder will remain open to thru traffic,
however, Reytec will have traffic control set up
in this section to complete the sidewalk, striping and
tree planting construction.
The
project is ahead of schedule with 92% complete.
The Calder Street Project Phase II
began construction on August 17, 2009. The project
limits of this phase of the project are from just west
of M.L. King Parkway to IH 10 east R.O.W. The contractor
BRH Garver plans on installing box culverts and
relocating water and sanitary sewer this week.
On August 25, 2009 the road will be closed from
1st street to 4th street for approximately 71 days. Only
local access and emergency vehicles will have access.
Today BRH Garver will begin excavating material from the
Calder roadway between 1st street and 4th
street on the north run of box. Garver has install box
from 1st to 3rd street on the
south run as of this week. The north run of box will
begin this week at 1st street and continue
westward to 4th street. Material will be
transported in and out of the project site along North
Street. Residents on North street from 1st
street to IH 10 please be aware of the increase in truck
traffic in this area. The water and sanitary sewer
relocation will continue to 7th street in the
upcoming weeks. We will give an update in advance of the
future street closures. 4th street was closed
to thru traffic on Monday October 12, 2009 for water
relocation work. This work will last approximately four
weeks. Garver plans on removing trees between 7th
and 8th streets this week. Traffic will be
controlled to one lane in each direction.
Project
contacts are listed below if additional information is
needed.
Reytec Construction, Phase
I Tommy Gill (281) 924-5842
BRH Garver, Phase II Todd
Hendricks (713) 254-7991
City of Beaumont Zheng Tan
(409) 880-3725
City of Beaumont JP Colbert
(409) 880-3725
City of Beaumont Damon
Jones (409) 880-3725
|
UPDATE: Gladys Street Project
|
Improvements to Gladys Street, planned
from the IH-10 West Frontage Road to Dowlen Road, are
scheduled to begin in 2011.
PLEASE NOTE
-
Plans
for a continuous turn lane between Edson and Dowlen have
been changed. The city no longer plans to add a
continuous turn lane on this section of Gladys.
-
The
city installs sidewalks during each road construction
project. The installation of sidewalks on both sides of
Gladys for the entire length of the project will be
discussed on Thursday, Oct. 8, at 6 p.m., at the Rogers
Park Community Center. Residents are invited to
participate.
-
The
city is surveying Gladys Street to identify property
corners, pavement widths, street intersections, natural
ground and infrastructure elevations, public and
city-owned utilities, driveways, drainage structures,
and more. Stakes or other markers placed in yards are an
indication of public right-of-way, and do not indicate
points to which Gladys will be widened. They are a
routine aspect of surveying during any project's
engineering phase.
Although specifics
regarding individual properties are not known at this time,
residents may contact the city concerning the overall
project by calling city services at 311, or the Engineering
Division at 880-3725.
|