Home | Driving Directions | Calendar

  

 Capital Improvement Projects

UPDATE: Calder Street Project

Update for the week of November 2, 2009

The Calder Street Project Phase I began construction on July 7, 2008. The project limits of this phase of the project are from the Neches River to just west of ML King Parkway. The Box Installation has been completed for the South and North runs from the Neches River to the end of the project. Reytec plans on having the M.L. King / Calder intersection open with the traffic signals in operation this week.

The concrete pavement has been installed on Calder to the radii of return on M.L. King. Reytec plans on installing brick pavers, decorative lighting, traffic signals, landscaping and bicycle lanes on Calder Avenue as part of the project. Reytec continues to install signage from Main St. to M.L. King on Calder Avenue this week. Reytec continues to work on the section of pavement from Magnolia Avenue to M.L. King on Calder.  Calder will remain open to thru traffic, however, Reytec will have traffic control set up in this section to complete the sidewalk, striping and tree planting construction.

The project is ahead of schedule with 92% complete.

The Calder Street Project Phase II began construction on August 17, 2009. The project limits of this phase of the project are from just west of M.L. King Parkway to IH 10 east R.O.W. The contractor BRH Garver plans on installing box culverts and relocating water and sanitary sewer this week.  On August 25, 2009 the road will be closed from 1st street to 4th street for approximately 71 days. Only local access and emergency vehicles will have access. Today BRH Garver will begin excavating material from the Calder roadway between 1st street and 4th street on the north run of box. Garver has install box from 1st to 3rd street on the south run as of this week. The north run of box will begin this week at 1st street and continue westward to 4th street. Material will be transported in and out of the project site along North Street. Residents on North street from 1st street to IH 10 please be aware of the increase in truck traffic in this area. The water and sanitary sewer relocation will continue to 7th street in the upcoming weeks. We will give an update in advance of the future street closures. 4th street was closed to thru traffic on Monday October 12, 2009 for water relocation work. This work will last approximately four weeks. Garver plans on removing trees between 7th and 8th streets this week. Traffic will be controlled to one lane in each direction.

Project contacts are listed below if additional information is needed.

Reytec Construction, Phase I Tommy Gill (281) 924-5842

BRH Garver, Phase II Todd Hendricks (713) 254-7991

City of Beaumont Zheng Tan (409) 880-3725

City of Beaumont JP Colbert (409) 880-3725

City of Beaumont Damon Jones (409) 880-3725

 

UPDATE: Gladys Street Project 

Improvements to Gladys Street, planned from the IH-10 West Frontage Road to Dowlen Road, are scheduled to begin in 2011.

PLEASE NOTE

  • Plans for a continuous turn lane between Edson and Dowlen have been changed. The city no longer plans to add a continuous turn lane on this section of Gladys.

  • The city installs sidewalks during each road construction project. The installation of sidewalks on both sides of Gladys for the entire length of the project will be discussed on Thursday, Oct. 8, at 6 p.m., at the Rogers Park Community Center. Residents are invited to participate.

  • The city is surveying Gladys Street to identify property corners, pavement widths, street intersections, natural ground and infrastructure elevations, public and city-owned utilities, driveways, drainage structures, and more. Stakes or other markers placed in yards are an indication of public right-of-way, and do not indicate points to which Gladys will be widened. They are a routine aspect of surveying during any project's engineering phase.

Although specifics regarding individual properties are not known at this time, residents may contact the city concerning the overall project by calling city services at 311, or the Engineering Division at 880-3725.